Crews Reach Halfway Point on Construction of 10-Mile Pipeline

5/29/2014

0 Comments

 
Carlsbad, CA (May 29, 2014) – The 10-mile pipeline that will connect the Carlsbad Desalination Plant to the San Diego County Water Authority’s distribution system is 50 percent complete, Poseidon Water and the Water Authority announced today. Approximately five miles – or 26,400 linear feet – of the large-diameter pipe has been installed through San Marcos, Vista and Carlsbad.
When finished, the Carlsbad Desalination Project will be the largest, most technologically advanced and energy-efficient seawater desalination plant in the Western Hemisphere. It will produce up to 50 million gallons a day and account for about one-third of all the water generated in San Diego County, helping reduce reliance on imported water as part of the Water Authority’s multi-decade strategy to enhance the region’s water supply reliability. In 2020, the project will meet about 7 percent of the region’s water demand.

“Through the construction of the Carlsbad Desalination Project, we are working to deliver enough high-quality, fresh drinking water to serve approximately 112,000 San Diego County households,” said Peter MacLaggan, Vice President of Poseidon Water, the project’s private developer. “A project of this size is an enormous task that impacts the communities where we are working, and we would not be celebrating this milestone without the cooperation and support of the residents, businesses, property owners and city staff in Carlsbad, Vista and San Marcos.”

Pipeline installation began in spring 2013 in San Marcos, where street restoration is under way. Restorations are also occurring in Vista this month. Construction in Carlsbad, home to the largest portion of the pipeline, is ongoing. Crews recently installed a critical segment of pipeline along Cannon Road east of Interstate 5, and they are working around the clock to install pipeline along Faraday Avenue. Additionally, pipeline installation on South Melrose Drive began this month and is expected to continue through 2015.

“We are thrilled with the smooth progress of construction on this vital project,” said Maureen Stapleton, general manager of the Water Authority. “Current statewide drought conditions underscore the value of diversifying the water supplies that support our region’s 3.1 million residents, and the Carlsbad Desalination Project is an important part of our strategy to enhance water supply reliability.”

This $1 billion Carlsbad Desalination Project is the result of a 30-year Water Purchase Agreement between the Water Authority and Poseidon Water for the purchase of up to 56,000 acre-feet per year of desalinated seawater. It includes three main components: the desalination plant, the pipeline, and about $80 million in upgrades the Water Authority is making to its facilities so it can distribute the desalinated water throughout the region. The project is scheduled to be online by early 2016, though deliveries could begin as soon as fall 2015.

During the three-year construction process, the desalination project is supporting an estimated 2,500 jobs and infusing $350 million into the local economy.

For more information about the Carlsbad Desalination Project, visit the project website at www.carlsbaddesal.com, or the Water Authority’s website, www.sdcwa.org. 
# # #
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    ​What's the latest?


    ​Jessica H. Jones

    ​Director of Communications
    Poseidon Water

    (760) 655-3998
    Contact

    ​Read news releases, newspaper articles and other bulletins about the Carlsbad Desalination Project and related topics here. Check back often for updates.
    Picture

    Categories

    All
    Awards And Accolades
    Construction Updates
    News Coverage
    News Release
    Press Releases

    Archives

    March 2022
    August 2020
    July 2020
    March 2020
    October 2019
    September 2019
    May 2019
    February 2019
    January 2019
    December 2018
    October 2017
    April 2017
    December 2016
    November 2016
    July 2016
    June 2016
    April 2016
    December 2015
    June 2015
    October 2014
    September 2014
    June 2014
    May 2014
    April 2014
    January 2014
    October 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    January 2012
    October 2011
    September 2011
    August 2011
    June 2011
    February 2011
    December 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    RSS Feed

HOME | DESAL 101 | NEWS | ENVIRONMENTAL | FAQS | ABOUT | CONTACT
© 2017 Carlsbad Desalination Project : 5780 Fleet Street, Suite 140, Carlsbad, CA 92008 | (760) 655-3900
​All Rights Reserved. Contact | Login.
  • Home
  • Desal 101
    • How it Works
  • News
    • Media Portal
  • Environmental
    • EIR
  • FAQs
    • Process FAQs
    • Environmental FAQs
  • About
    • Who We Are
    • What We Do
    • How We Do It
    • Construction >
      • Mitigation
      • Intake and Outfall
      • Pipeline Overview
      • Desal Plant
      • Construction Team
  • Contact
    • Visit
    • Careers
    • Privacy policy