Title: Permitting



 
 
CarlsBad

Environmental Impact Report: Completed

  • Lead Agency: City of Carlsbad
  • Draft EIR: May 2006
  • Final EIR: Certified June 13, 2006
CarlsBad

Local Land Use Permits: Completed

  • Responsible Jurisdiction: City of Carlsbad
  • Local Coastal Development Permit: N/A
  • Conditional Use Permit: Approved June 13, 2006

Discharge (NPDES) Permit: Completed

  • Responsible Agency: Regional Water Quality Control Board
  • NPDES: Approved August 16, 2006
DHS Logo

Drinking Water Permit: Completed

  • Responsible Agency: CA Department of Health Services
  • Conditional Drinking Water Permit: Approved October 19, 2006

Coastal Development Permit (CA only): Completed

  • Responsible Agency: CA Coastal Commission
  • Application: Submitted August 2006
  • Notice of Incomplete (1):
    • Received - September 2006
    • Response – November 2006
  • Notice of Incomplete (2):
    • Received - December 2006
    • Response – January 22, 2007
  • Notice of Incomplete (3):
    • Received - February 2007
    • Response - June 4, 2007
  • Notice of Incomplete (4):
    • Received - July 3, 2007
    • Response - July 16, 2007
  • Coastal Development Permit: Approved November 15, 2007
  • Permit conditions: Approved August 6, 2008

State Lands Commission (CA only): Completed

  • Lease Application: Submitted February 2007
  • Notice of Incomplete:
    • Received - March 5, 2007
    • Response - June 15, 2007
  • Lease Application approved: August 22, 2008
.