The first segment of pipeline construction is currently under way in San Marcos at Rancho Santa Fe Road and Creek Street. On April 1, construction near Saint Joseph Academy on Las Flores and 9th Street will begin and work will travel east on 9th Street toward Rancho Santa Fe Road. On April 18, construction on Poinsettia Avenue and W. Linda Vista Drive will begin and travel south on Poinsettia Drive toward Specialty Drive. On April 29th, work on Las Flores Drive will travel from Saint Joseph Academy south toward W. Linda Vista Drive. Finally, on June 1, work will begin on W. Linda Vista Drive from Las Flores Street toward Poinsettia Avenue. Construction work in San Marcos is expected to be completed by August 2013. Stay tuned for more updates as construction continues on the desalination pipeline.